The main line bridge of the ZCB1-7 project of the Nanjing (South) Panzhihua (Zhihua) Expressway, which was constructed by Sichuan Road Group, has been completed recently, laying a solid foundation for the early realization of the opening target of the Ningji-Panzhihua expressway.
There are 5 main Bridges and 5 middle Bridges in the ZCB1-7 project of Ningpan Section, with a total of 395 T-beams installed. Project construction is faced with frequent extreme weather, complex geological conditions and high environmental protection requirements. In order to ensure the completion of bridge construction before the rainy season, the project adopts the drive of "approach is sprint, start is decisive battle" to strengthen personnel, integrate resources and equipment, optimize construction plan, correct errors scientifically and timely. At the same time, it compacts and compacts responsibility, manages and manages the "responsibility field" of safe production. Ensure the safety, quality and schedule of the whole process of bridge erection, including human, mechanical, material, method and environment.
Mission in the shoulder, forge ahead. All the construction personnel of Yanjiang Expressway will continue to beat the war drum, sprint to full strength, focus on the remaining target nodes, promote the project production and construction efficiently and orderly, and strive to create "green, smart, tourism and industry along the river", so as to make greater contributions to the establishment of "century-old quality Project of safety" of Yanjiang Expressway.